Cement Mortar Lining (CML) to a 3000mm diameter M.S. pipeline
Project information
Service Provided
Internal Cement Mortar Lining
Duration of work
5 months
Completion Date
15 Feb 2022
Ready Your Next Construction?

19000 sqm

Private, Semi - Govt

Dhamangaon, Bhiwandi, Mumbai

Pictures or videos of a Project
Project information
Client
SMC Infra
Location
Dhamangaon, Bhiwandi, Mumbai
Completion Date
30 December 2023
Ready For Your Next Project?
Call us any time

Providing Internal Cement Mortar Lining (CML) to a 3000mm diameter M.S. pipeline. The lining thickness was 12mm using CM 1:1 mortar. The work included manual cleaning, lining, 7 days curing, cutting, and rewelding of access openings for machine and personnel, using our own machinery, manpower, and consumables.

Conducted using our own specialized machines combined with manual brushing to clean internal rust and grease from the pipe.

Godhara sand for mortar preparation.

7 days to ensure proper setting and durability of the lining.

AWWA C205 and ISO 4179 to maintain quality and industry compliance.

Successfully completed lining over 20,000 sqm. During the project, we faced challenges such as material delays, uncertain weather conditions, and excessive heating of the pipeline during summer months. This heating caused small cracks in the CML. To overcome this, we implemented continuous cooling of the pipeline before work and strategically scheduled most of the work during nighttime, ensuring quality and timely completion.

Pictures or videos of a Project